12%,靜態(tài)投資回收期:"/>
【摘 要】項目區(qū)節(jié)水灌溉面積0.5萬畝,工程總投資420萬元,年運行費758.4萬元,經(jīng)濟內(nèi)部收益率:13.1%>12%,靜態(tài)投資回收期:6.28年<8年,經(jīng)濟凈現(xiàn)值15.4萬元,經(jīng)濟效益費用比1.002>1.0,項目經(jīng)濟合理。
【關(guān)鍵詞】節(jié)水灌溉;經(jīng)濟評價
Economic efficiency evaluation of water-saving irrigation project
Wang Zhi-wei
(Zhangwu County, Liaoning Province, Hal sets of town water conservancy stations Zhangwu Liaoning 123221)
【Abstract】0.5 million mu water-saving irrigation area of the project area, total project investment of $ 4.2 million, 7.584 million yuan of annual operating costs, the economic internal rate of return: 13.1%> 12% Static payback period: 6.28 years <8 years, the economic net present value15.4 million economic benefit costs than 1.002> 1.0, the project of economic rationality.
【Key words】Water-saving irrigation;Economic evaluation
1. 基本資料
項目區(qū)節(jié)水灌溉面積0.5萬畝,全部種植加工型馬鈴薯,平均畝產(chǎn)3000Kg.水澆地項目中巖石井運行年限為15年,管路運行年限為12年,為確保農(nóng)民利益準(zhǔn)確合理的進行效益分析,本工程效益分析以12年為依據(jù)。
2. 工程總投資與費用
工程總投資420萬元
年運行費:節(jié)水灌溉工程在正常運行期間所需的費用包括:燃料動力費、維修費和生產(chǎn)管理費、水費、種植成本及人工費。
燃料動力費:機組噴灌機械耕作經(jīng)濟作物400元/畝;維修管理費:按建安總投資的2%;水費:機組噴灌經(jīng)濟作物100元/畝;植成本及人工費: 500元/畝,化肥200元,農(nóng)藥150元,整地費100元,人工費50元。
年運行費C=燃料動力費+維修管理費+水費+種植成本
3.4 投資回收期Pt
投資回收期:
Pt=累計凈現(xiàn)金流量開始出現(xiàn)正值的年份-1+(上年累計凈現(xiàn)金流量的絕對值/當(dāng)年凈現(xiàn)金流量)
經(jīng)過計算Pt=6.28年
4. 評價結(jié)果
4.1 經(jīng)濟內(nèi)部收益率:13.1%>12%
4.2 靜態(tài)投資回收期:6.28年<8年
4.3 經(jīng)濟凈現(xiàn)值15.4萬元遠大于零,經(jīng)濟合理。
4.4 經(jīng)濟效益費用比1.002>1.0該項目經(jīng)濟合理。
[文章編號]1619-2737(2015)05-22-67
[作者簡介] 王志偉(1960.5.1-),男,學(xué)歷:本科,工作單位:彰武縣哈爾套鎮(zhèn)水利站,2009年1月畢業(yè)于寧工業(yè)大學(xué)土木工程專業(yè),從事水利工程管理工作。